August 29, 2019: Racking is almost complete, and panel installation is at 25%. Thank you neighbors for your patience during construction, we are getting closer everyday!

Simsbury Meadows Performing Arts Center will be hosting Circus Smirkus in July 30 - 31, 2019. Tobacco Valley Solar is happy to be a sponsor! Please consider attending one of their exciting performances: http://simsburymeadowsmusic.com/events/circus-smirkus-carnival/

June 17, 2019: Pile installation is ongoing, solar panel deliveries will begin today.

June 5, 2019: Pile installation has begun and will continue for the next few weeks.

May 28, 2019: Pile deliveries will begin Tuesday 5/28, pile installation will begin shortly after delivery.

May 15, 2019: Tree clearing was completed (May 14), grubbing of cleared areas is nearly complete.

April 2019: Grass seeding of the Project area fields and tree clearing in certain areas will begin this month.

March 2019: Tobacco Valley Solar’s Development and Management Plan was approved by the CT Siting Council on March 28, 2019, and the Project’s Stormwater Pollution Control Plan was approved by the CT Dept. of Energy and Environmental Protection on March 27, 2019.